Constant improvement
Our company pays great attention to improve our CCM exam materials: Certified Case Manager Certification Exam (CCM). Our aim is to develop all types study material about the official exam. Then you will relieve from heavy study load and pressure. Also, our researchers are researching new technology about the CCM learning materials. After all, there always exists fierce competition among companies in the same field. Once we stop improve our CCM study guide, other companies will soon replace us. The most important reason is that we want to be responsible for our customers. They give us strong support in the past ten years. Luckily, our CCM learning materials never let them down. Our company is developing so fast and healthy. Up to now, we have made many achievements. Also, the CCM study guide is always popular in the market. All in all, we will keep up with the development of the society.
Good reputation
Our CCM exam materials: Certified Case Manager Certification Exam (CCM) are the most reliable products for customers. If you need to prepare an exam, we hope that you can choose our CCM study guide as your top choice. In the past ten years, we have overcome many difficulties and never give up. Fortunately, we have survived and developed well. So our company has been regarded as the most excellent seller of the CCM learning materials. We positively assume the social responsibility and manufacture the high quality study materials for our customers. Never have we made our customers disappointed about our CCM study guide. So we have enjoyed good reputation in the market for about ten years. In the future, we will stay integrity and research more useful CCM learning materials for our customers. Please continue supporting our products.
Life is always full of ups and downs. You can never stay wealthy all the time. So from now on, you are advised to invest on yourself. The most valuable investment is learning. Perhaps our CCM exam materials: Certified Case Manager Certification Exam (CCM) can become your top choice. Our study materials have won many people's strong support. Now, they have gained wealth and respect with the guidance of our CCM learning materials. At the same time, the price is not so high. You totally can afford them. Do not make excuses for your laziness. Please take immediate actions. Our CCM study guide is extremely superior.
Smooth operation
Our online test engine and the windows software of the CCM exam materials: Certified Case Manager Certification Exam (CCM) will greatly motivate your spirits. The exercises can be finished on computers, which can help you get rid of the boring books. The operation of the CCM study guide is extremely smooth because the system we design has strong compatibility with your computers. It means that no matter how many software you have installed on your computers, our CCM learning materials will never be influenced. Also, our CCM study guide just need to be opened with internet service for the first time. Later, you can freely take it everywhere. Also, our system can support long time usage. The durability and persistence can stand the test of practice. All in all, the performance of our CCM learning materials is excellent. Come to enjoy the pleasant learning process. It is no use if you do not try by yourself.
Medical Professional Certified Case Manager Certification Exam (CCM) Sample Questions:
1. You are the Contract Manager of the Engineer and person Y is the Contract Manager of the Employer in a construction project under FIDIC 2017 Red Book. The project is late in schedule and Y has issued Employer ' s claim on Delay Damages. You have asked Y to consider whether the Contractor ' s delay to completion is a reflection of cash-flow shortfall from interim payments before making deductions to the Contractor ' s payment. Y replied that even if the Contractor pays Delay Damages to the Employer, the Contractor is still obliged to complete the Works and is not relieved from its duties and obligations. You warned Y of the risks of further reduction of cash-flow by the deduction of Delay Damages from payments. As this could worsen the situation of the Contractor, leading to further delays to the completion of the Works. Who is right?
A) You are correct, Y is wrong.
B) Both you and Y are wrong.
C) Both you and Y are both correct.
D) You are wrong, Y is correct.
2. Which one statement is correct regarding the FIDIC Red Book (edition 2017)?
A) No Data other than required by the General Conditions of Contract may be entered in the Contract Data.
B) General Conditions of Contract cannot be amended as it may imbalance the obligations and rights of the Parties.
C) Instructions to Tenderers are part of the Employer ' s Requirements.
D) Instructions to Tenderers may require the tenderer to provide information on matters in Sub-Clause 4.3 on Contractor ' s Representative and Sub-Clause 6.12 on Key Personnel.
3. (You are the Contract Manager for the Engineer in a highway project using FIDIC Red Book (edition 1999).
There is a Schedule of cost indexation included in the Contract. The project must be completed by 31 December of this year. If the Contractor fails to complete the Works by then, how will the adjustment of prices take place thereafter? (1 correct answer applies))
A) Each index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works.
B) Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is agreed by the Parties.
C) Either the current index/price, or index or price applicable on the date 49 days before the expiry of the Time for Completion of the Works, whichever is more favourable to the Employer.
D) The current index or price.
4. Which one of the following is not a required document to be submitted by the Contractor if the Employer requests a proposal, prior to instructing a Variation, for FIDIC 2017 Yellow Book?
A) A description of the varied work.
B) A description of the proposed design.
C) Details of the resources and methods to be adopted by the Contractor.
D) A Programme for execution of the varied work.
5. Which one of the following statements is correct regarding the Provisional Sum under the FIDIC Red, Yellow, and Silver Books (edition 1999)?
A) The Provisional Sum cannot be issued by instruction either by the Engineer (or Employer in case of FIDIC Silver Book).
B) The Contractor shall, when required by the Engineer, produce proof to substantiate how it has used the Provisional Sum.
C) Each Provisional Sum shall not be used, in whole or in part, in accordance with instructions from the Engineer.
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: D | Question # 3 Answer: C | Question # 4 Answer: B | Question # 5 Answer: B |